The 2nd construction plan (draft) of KIST Europe
- Site: Campus E 71, 66123 Saarbruecken, Germany
- Budget : 4,3 Mio. Euro
- 15% from Saarland government
- 85% from Korean government
- Area: 1,920.6 m2 (582 pyong)
- Area plan: office, laboratory and lecture room
- Utilization plan
- On Site Lab for Korean Research Organizations including KIST
- Korea EU S&T "Cooperation-Platform"
- Korean Universities Europe Campus
- Construction Duration: Jan 2007 - Feb. 2010
- 2007: Planning
- 2008 - 2010: Construction
- 2010: Completion